Weekly Status Update
We’re excited to share that the project at the L Building is underway, and the contractor has made progress this week.
Here’s what has been accomplished so far:
Construction fencing has been installed around the jobsite
The interior of units have been photographed, with the exception of a few units where we have communicated with the owners regarding access issues.
Several crews of workers are on-site working on the demolition of the decks and siding. The demo started on both ends of the building, with the crews working toward the middle.
Next Week's Schedule
The contractor will continue with the demolition phase. The contractors plan to work on Saturday for a portion of the day. The removal of the remaining decks and siding is expected to be completed next week.
IMPORTANT – DECK ACCESS OFF LIMITS
This is an important reminder that the rear decks of the L Building have been removed or will be removed in the coming days as part of the construction project.
For everyone’s safety, please ensure that all sliding glass doors leading to the rear remain locked throughout the construction period. If you have renters or guests occupying your villa, we kindly ask that you notify them of the absence of rear decks and the importance of keeping these doors secured from the inside.
Should you choose to occupy your unit or allow guests to do so during the construction period, you assume full responsibility and liability for their safety. The Harbor Island Beach House shall not be held liable for any injuries or damages that may occur as a result of occupancy during the construction phase of the project.
Below are photos showing the current status of the project as of November 7th.
Thank you for your cooperation and continued support as we move through this phase of the renovation.
In your service,
Coastal Resort Association Management






Weekly Status Update
Even with a short week due to the observance of Veterans Day and with no construction permitted on the Island on Tuesday, the contractor still made great progress.
Here’s what has been accomplished so far:
Next Week's Schedule
Next week, the contractor will begin removing the existing windows and sliding doors, covering the openings with plywood, and preparing the rough openings for the new windows and doors.
Plywood will remain over the window and door rough openings until the engineer inspects the framing and the new sheathing is installed. This work will be completed in sections. The contractor will begin on the side of the building farthest from the beach and work toward the villas closest to the beach.
We expect the contractor to be working at units 112, 212, 312, 111, 211, 311, 110, 210, 310, 109, 209, and 309 next week.
IMPORTANT – DECK ACCESS OFF LIMITS
This is an important reminder that the rear decks of the L Building have been completely removed.
For everyone’s safety, please ensure that all sliding glass doors leading to the rear remain locked. If you have renters or guests occupying your villa, we kindly ask that you notify them of the absence of rear decks and the importance of keeping these doors secured from the inside.
Should you choose to occupy your unit or allow guests to do so during the construction period, you assume full responsibility and liability for their safety. The Harbor Island Beach House shall not be held liable for any injuries or damages that may occur as a result of occupancy during the construction phase of the project.
Attached are photos showing the current status of the project as of November 14th.
Thank you for your cooperation and continued support as we move through this phase of the renovation.
In your service,
Coastal Resort Association Management



Weekly Status Update
The contractor made good progress this week, removing the existing windows and doors and reframing the rough openings for the new windows and preparing the rough openings for the new sliding doors. The following units have had their windows and doors removed, and the new rough openings have been completed: L112, L212, L312, L111, L211, L311, L110, L210, L310, L109, L209, L309, L108, L208, L308, L107, L207, L307, L106, L206, L306.
The contractors will also be working on Saturday and plans to remove the windows and doors in the following units: L105, L205, L305, L104, L204, L304.
Next Week's Schedule
On Monday, the structural engineer will be on-site to inspect the framing in the units that were completed this week. If all goes well with the inspection, the contractor will begin installing the new sheathing after the inspection on Monday.
The contractor will also be removing the windows and doors at the following units on Monday and Tuesday: L103, L203, L303, L102, L202, L302, L101, L201, L301.
Plywood will remain over the windows and doors openings until the new windows and doors are installed.
IMPORTANT – DECK ACCESS OFF LIMITS
This is an important reminder that the rear decks of the L Building have been completely removed.
For everyone’s safety, please ensure that all sliding glass doors leading to the rear remain locked. If you have renters or guests occupying your villa, we kindly ask that you notify them of the absence of rear decks and the importance of keeping these doors secured from the inside.
Should you choose to occupy your unit or allow guests to do so during the construction period, you assume full responsibility and liability for their safety. The Harbor Island Beach House shall not be held liable for any injuries or damages that may occur as a result of occupancy during the construction phase of the project.
Attached are photos showing the current status of the project as of lunchtime on November 14th. Please note, the units shown in one of the photos that were open and uncovered were actively being worked on and have since been boarded up.
Thank you for your cooperation and continued support as we move through this phase of the renovation.
In your service,
Coastal Resort Association Management






Weekly Status Update
The following units were inspected by the structural engineer and were approved to have the sheathing installed: L112, L212, L312, L111, L211, L311, L110, L210, L310, L109, L209, L309. The contractor has begun installing new permanent sheathing at these units and will be complete or very close to complete by the end of today, installing new sheathing at units L112, L212, L312, L111, L211, and L311.
The following units have not had the windows and doors removed yet: L101, L201, L301, L102, L202, L302, L103, L203, L303. The current plan is to catch up with sheathing installation on the inspected units before removing the remaining windows and doors.
The contractor will not be working the remainder of the week.
Next Week's Schedule
On Monday, December 1st, the contractor will resume installing new sheathing at units that have been inspected. The engineer is tentatively scheduled to be back onsite next Tuesday to inspect units L108, L208, L308, L107, L207, L307, L106, L206, L306, L105, L205, L305, L104, L204, L304. There is a good chance that the contractor begins to install sheathing on these units toward the middle-end of next week.
IMPORTANT – DECK ACCESS OFF LIMITS
This is an important reminder that the rear decks of the L Building have been completely removed.
For everyone’s safety, please ensure that all sliding glass doors leading to the rear remain locked. If you have renters or guests occupying your villa, we kindly ask that you notify them of the absence of rear decks and the importance of keeping these doors secured from the inside.
Should you choose to occupy your unit or allow guests to do so during the construction period, you assume full responsibility and liability for their safety. The Harbor Island Beach House shall not be held liable for any injuries or damages that may occur as a result of occupancy during the construction phase of the project.
Below are photos showing the current status of the project as of lunchtime on November 26th.
Thank you for your cooperation and continued support as we move through this phase of the renovation.
In your service,
Coastal Resort Association Management





Copyright © 2025 Beach House & Ocean Villas Owners Community - All Rights Reserved.